Isostatic Toll Services is committed to providing our customers
with the highest quality in the industry.
Our company currently has quality systems certified to:
- NADCAP AC7102/6:HIP (Click for Certificates)
- ISO 9001/AS9100 (Aerospace) (Click for Certificate)
Supplier Flow-Down Requirements
Scope.
These requirements apply to all suppliers and their sub-tier suppliers providing:
A. Equipment, parts, materials, and services used in Hot Isostatic Presses (HIP) builds or fielded systems; and/or
B. Isostatic toll services (e.g., HIP/CIP) performed on our or our customers’ parts.
Baseline Quality Standards
- Maintain and apply an effective quality management system compliant with AS9100D (or ISO 9001:2015 with aviation add-ons as applicable).
- For aerospace engine/rotating components or where specified, comply with AS13100 supplemental quality requirements.
- For special processes (e.g., HIP/CIP, heat treat, NDT, coatings), hold and maintain NADCAP accreditation for the relevant process, when specified on the PO.
1) Regulatory & Ethical Compliance
- Comply with all applicable laws and regulations (including product safety, environmental, and export controls such as ITAR/EAR).
- Prevent counterfeit or suspect/unapproved parts; use traceable, authorized sources only.
- Adhere to high standards of business ethics and employee safety; report concerns that may affect product conformity or safety.
2) Configuration, Design, and Changes
- (Design & Development—ISO 9001:2015 8.3): When providing design/development, implement documented 8.3 controls (planning, inputs, reviews, verification, validation, outputs, and controlled changes). Provide design records and risk assessments upon request.
- Change Control (All): Do not change materials, process, equipment, facility location, sub-tiers, or key personnel qualifications without prior written approval. Notify us of any potential obsolescence or substitution.
3) Special Process Control (HIP/CIP/WIP and other NADCAP processes)
- Execute only to approved procedures and current specifications listed on the PO/drawing.
- Record and retain complete run data (e.g., load map, temperature/pressure/vacuum profile, hold times, cooling rates, equipment ID, sensor IDs, lot/serial traceability). Provide upon request or with shipment when required.
- Maintain calibrated instrumentation and qualified operators; perform periodic system accuracy checks and leak-checks.
- Manage pyrometry and pressure/temperature measurement to current industry standards and internal procedures (retain objective evidence).
4) Product Conformity, Inspection & Test
- Implement inspection and verification to the PO/drawing/specification, including key and critical characteristics where identified.
- Provide a Certificate of Conformance (CoC) with each shipment stating: PO number, part number/rev, serial or lot numbers, quantity, specs/revisions applied, and statement of conformity. Include raw material certifications and special process certificates, as applicable.
- Use suitable packaging to prevent FOD/damage; identify each package with part number, quantity, and traceability.
5) Nonconformance & Corrective Action
- Do not ship known nonconformances without our written deviation/waiver.
- If a nonconformance is discovered post-delivery, notify us within 24 hours with full containment and risk assessment.
- Respond to corrective action requests with root cause, containment, corrective and preventive actions, and effectiveness evidence by the due date.
6) Traceability & Record Retention
- Maintain full traceability from raw material through final product and special processes.
- Retain quality and production records (including design, calibration, lot history, HIP/CIP run charts, CoCs) for minimum 10 years unless otherwise specified; do not destroy records without written approval.
7) Right of Access & Customer Requirements
- Provide right of access for our organization, our customers, and regulatory authorities to applicable facilities, processes, records, and product.
- Flow down all applicable requirements—including key characteristics, special process controls, and these clauses—to sub-tier suppliers.
8) On-Time Delivery & Communication
- Meet the PO delivery date(s); notify us immediately of any risk to schedule or conformity.
- Provide advance notice for any capacity constraints affecting our orders.
9) Measurement & Calibration
- Use calibrated inspection, test, and monitoring equipment traceable to national/international standards. Keep calibration records available.
10) Additional AS13100 Expectations (when invoked on PO)
- Apply risk-based APQP/PPAP-style planning, process capability for key characteristics, MSA where applicable, robust change management, and escape management aligned to AS13100. Provide control plans and FAIR/PPAP packages upon request.
Next Steps...
We are available to discuss your hot isostatic pressing needs. Work with experienced technicians who can assist with optimizing your run parameters based on product requirements.